Project Introduction: The Mumbai metro is a rapid transit system being developed by both the PPP (Public-Private Partnership) and EPC models. Line 1 and Line 2 are being developed with Reliance as the consortium head while Line 3 is going to be developed by an implementation agency called MMRC whose role is similar to the DMRC in the Delhi Metro project. Phase I
Code: Line # Route Length(Kms) Stations Special Purpose Vehicle
Line 1 Versova - Andheri - Ghatkopar 11.4 12 Mumbai Metro One Pvt. Ltd. Line 2 Charkop - Bandra - Mankhurd 32 27 Mumbai Metro Transport Pvt. Ltd. Line 3 SEEPZ - BKC - Colaba 33 25 Mumbai Metro Rail Corporation
Line 1 Versova-Andheri-Ghatkopar - 11.4 Kms - Under Construction
1) GENERAL
o Journey time: 21 minutes o Frequency: 3.5 minutes, going down to 3 minutes during peak hours o Fares # (2003-2004 level) + Rs. 6 upto 3 Kms. + Rs. 8 between 3 Kms.to 8 Kms. + Rs. 10 beyond 8 Kms.
# Fares indicated are for 2003-2004 level and shall be revised @ 11% every fourth year (rounded off to the nearest rupee). Fares shall be fixed by Government of Maharashtra, through a notification.
Line 2 Charkop - Bandra - Mankhurd - 32 Kms - Approved
Line 3 SEEPZ - BKC -
Colaba/Cuffe Parade - 33 Kms - Planning stage